Start with the datasheet figure
Every Marindec technical data sheet (TDS) gives a theoretical spread rate: the square metres one litre covers at a stated dry film thickness (DFT). It assumes a smooth surface and no paint lost along the way.
The figure comes from the paint's volume solids, the part of the paint left on the surface once the solvent evaporates. Coverage (m²/L) = volume solids (%) × 10 ÷ DFT (µm). For FPW15 primer that is 15 × 10 ÷ 20 = 7.5 m²/L; its datasheet states 7.7.
| Product | Theoretical coverage | At dry film thickness |
|---|---|---|
| FPW15 and ZPPW15 primers | 7.7 m²/L | 20 µm |
| EPS15 etch primer | 9.6 m²/L | 12.5 µm |
| Galvanised Iron Primer | 5 m²/L | 70 µm |
| Fast Dry Enamel | 7.35 m²/L | 30 µm |
| Hammertone | 10.7 m²/L | 30 µm |
| AGRIP30+ high build | 8.0 m²/L | 40 µm |
| 2K polyurethane | 12 m²/L | 40 µm |
| High Gloss Enamel | 11–15 m²/L | 35 µm |
| Super Gloss Enamel | 9–11 m²/L | 25–35 µm, depending on the surface |
| Floor & Stoep Enamel | 7.5 m²/L | 45 µm |
| Road marking paint | 4–5 m²/L | 150 µm |
| Heat Resistant Aluminium | 4.5 m²/L | 20 µm |
Real coverage is lower
Most Marindec datasheets say practical coverage is 50–70% less than theoretical, depending on the surface and how the paint is applied. Spray loss, rough or blasted steel, and paint left in tins and lines all count.
In practice, that means two to three times the theoretical litres. Where a job lands in that range depends on the surface and the method, so measure on the first day and adjust the order.
A worked example
Say you are painting 200 m² of steelwork with one coat of ZPPW15 at 20 µm and one coat of Fast Dry Enamel at 30 µm.
| Coat | Theoretical litres | Plan for (50–70% loss) |
|---|---|---|
| ZPPW15 primer, 20 µm | 200 ÷ 7.7 = 26 L | 52–87 L |
| Fast Dry Enamel, 30 µm | 200 ÷ 7.35 = 27 L | 54–91 L |
To get the planned figure, divide the theoretical litres by 0.5 for a 50% loss and by 0.3 for a 70% loss. For this job, three to four 25L drums of each product covers it.
A thicker coat covers less
Coverage falls in step with film thickness. AGRIP30+ covers 8 m²/L at 40 µm, so at 20 µm it would cover about 16 m²/L, and two coats need twice the paint of one.
Build to the film thickness the system needs, not to the coverage you hoped for. A film that is too thin saves paint now and costs a repaint later.
Lines and floors
A 100 mm line covers 1 m² every 10 metres. Road marking paint at 150 µm covers about 20–25 m² from a 5L tin, roughly 200–250 metres of line. The road marking guide has the detail.
Floor & Stoep Enamel works out at about 110–190 metres of 100 mm line per 5L tin per coat, after losses. See warehouse floor marking paint.
Check the film while you paint
The only way to know your real coverage is to measure. Check the wet film thickness (WFT) with a comb gauge as you apply, and compare the litres used with the area done after the first day. The film thickness measurement guide shows how.
For a quote, send us the area, the surface, the system and the number of coats. We'll work out the volumes with you, and quotes usually come back the same working day.