Start with the datasheet figure

Every Marindec technical data sheet (TDS) gives a theoretical spread rate: the square metres one litre covers at a stated dry film thickness (DFT). It assumes a smooth surface and no paint lost along the way.

The figure comes from the paint's volume solids, the part of the paint left on the surface once the solvent evaporates. Coverage (m²/L) = volume solids (%) × 10 ÷ DFT (µm). For FPW15 primer that is 15 × 10 ÷ 20 = 7.5 m²/L; its datasheet states 7.7.

ProductTheoretical coverageAt dry film thickness
FPW15 and ZPPW15 primers7.7 m²/L20 µm
EPS15 etch primer9.6 m²/L12.5 µm
Galvanised Iron Primer5 m²/L70 µm
Fast Dry Enamel7.35 m²/L30 µm
Hammertone10.7 m²/L30 µm
AGRIP30+ high build8.0 m²/L40 µm
2K polyurethane12 m²/L40 µm
High Gloss Enamel11–15 m²/L35 µm
Super Gloss Enamel9–11 m²/L25–35 µm, depending on the surface
Floor & Stoep Enamel7.5 m²/L45 µm
Road marking paint4–5 m²/L150 µm
Heat Resistant Aluminium4.5 m²/L20 µm

Real coverage is lower

Most Marindec datasheets say practical coverage is 50–70% less than theoretical, depending on the surface and how the paint is applied. Spray loss, rough or blasted steel, and paint left in tins and lines all count.

In practice, that means two to three times the theoretical litres. Where a job lands in that range depends on the surface and the method, so measure on the first day and adjust the order.

A worked example

Say you are painting 200 m² of steelwork with one coat of ZPPW15 at 20 µm and one coat of Fast Dry Enamel at 30 µm.

CoatTheoretical litresPlan for (50–70% loss)
ZPPW15 primer, 20 µm200 ÷ 7.7 = 26 L52–87 L
Fast Dry Enamel, 30 µm200 ÷ 7.35 = 27 L54–91 L

To get the planned figure, divide the theoretical litres by 0.5 for a 50% loss and by 0.3 for a 70% loss. For this job, three to four 25L drums of each product covers it.

A thicker coat covers less

Coverage falls in step with film thickness. AGRIP30+ covers 8 m²/L at 40 µm, so at 20 µm it would cover about 16 m²/L, and two coats need twice the paint of one.

Build to the film thickness the system needs, not to the coverage you hoped for. A film that is too thin saves paint now and costs a repaint later.

Lines and floors

A 100 mm line covers 1 m² every 10 metres. Road marking paint at 150 µm covers about 20–25 m² from a 5L tin, roughly 200–250 metres of line. The road marking guide has the detail.

Floor & Stoep Enamel works out at about 110–190 metres of 100 mm line per 5L tin per coat, after losses. See warehouse floor marking paint.

Check the film while you paint

The only way to know your real coverage is to measure. Check the wet film thickness (WFT) with a comb gauge as you apply, and compare the litres used with the area done after the first day. The film thickness measurement guide shows how.

For a quote, send us the area, the surface, the system and the number of coats. We'll work out the volumes with you, and quotes usually come back the same working day.