Three times on every datasheet

  • Touch dry: the surface no longer marks when touched lightly. The film underneath is still soft.
  • Hard dry: the film is dry through and can be handled.
  • Overcoat: when the next coat can go on. Some datasheets set a deadline ("within 2 hours"); others set a minimum wait ("minimum 6 hours").

All figures below are from each product's technical data sheet (TDS). They hold at normal temperatures and the stated film thickness.

Drying times by product

ProductTouch dryHard dryOvercoat
FPW15 and ZPPW15 primers± 10 min± 4 hWithin 2 h
EPS15 etch primer± 10 min± 1 hMinimum 1 h
Galvanised Iron Primer± 2 h± 6 hOvernight
Fast Dry Enamel± 10 min± 4 hWithin 2 h
Fast Dry Enamel, spray grade± 10 min± 1 hWithin 2 h
Hammertone± 15 min± 4 hWithin 2 h
AGRIP30+ high build10–30 min3–16 hWithin 2–3 h
2K polyurethane± 3 h± 8 hMinimum 6 h
High Gloss Enamel3–6 h12–16 h16–18 h
Super Gloss Enamel (at 25 °C)4 h18 h18 h
Floor & Stoep Enamel45–60 min4–8 hWithin 3–4 h
Road marking paintNot stated45 minNot stated
QD Bright Aluminium spray± 10 min± 30 minWithin 2 h
Heat Resistant Aluminium± 8 hHandle after ± 24 h± 36 h

What makes paint dry slower

  • Film thickness. A thick coat holds more solvent. AGRIP30+ is hard dry in 3 hours as a thin coat and up to 16 hours as a thick one.
  • Temperature. The gloss enamel and aluminium datasheets give times that depend on ambient temperature; Super Gloss Enamel's are quoted at 25 °C.
  • Moisture. Every datasheet asks for a dry surface at least 3 °C above the dew point. QD Bright Aluminium is very sensitive to moisture: rain, dew or high humidity after application can make it peel.

Plan the job around the overcoat window

Fast dry systems suit work that has to go back into service quickly. With ZPPW15 and Fast Dry Enamel, the enamel goes on inside the primer's 2-hour window, and the spray grade is hard dry about an hour later.

2K polyurethane runs to a slower clock. Wait at least 6 hours between coats, and mix only what you can apply within the ± 4-hour pot life at 23 °C. Galvanised Iron Primer needs to stand overnight before the topcoat.

If a job runs past an overcoat deadline, ask us before you apply the next coat.

Traffic, handling and heat

  • Keep forklifts and vehicles off Floor & Stoep Enamel until it is hard dry, 4–8 hours.
  • Road marking paint is hard dry in about 45 minutes, so a lane can reopen soon after marking.
  • Heat Resistant Aluminium develops its full properties only after baking, at least 45 minutes at 250 °C, and reaching operating temperature.

Need help planning coats around a shutdown? Request a quote with the system and the time you have, and we'll suggest the fastest system that suits the job. Thinning also changes how a paint behaves: see which paint thinner to use.